Grant Beach Park Box Rehabilitation

Project Facts

  • Start Date - July 9th, 2017
  • Completion Date - September 7, 2017
  • Contractor - Pfefferkorn & Drury Construction, LLC
  • Cost - $210,120 
  • Design Engineer - CJW Transportation Consultants, LLC
  • Design Features - Cast-in-place construction of approximately 300 linear feet of 7' x 4' reinforced concrete box culvert.
  • Funding - Stormwater Detention Buyout Fund
  • Location - Located within Grant Beach Park, northwest of the intersection of North Douglas and W Lynn Street
  • Objectives - Replacement of a 300 linear foot segment of deteriorated box culvert in Grant Beach Park that had reached the end of its useful life and the sidewalls and top of the box had failed. The top of the box culvert serves as an American's with Disabilities Act (ADA) compliant pedestrian walking surface.