Springfield Industrial Park Prince Lane

Project Facts

  • Start Date - January 21st, 2019
  • Completion Date - April 19th, 2019
  • Contractor - Hamilton & Dad, Inc.
  • Cost - $166,005.43
  • Design Engineer - CJW Transportation Consultants, LLC
  • Design Features - Approximately 750 linear feet of open channel improvements and stormwater piping as well as curb inlet improvements along North Prince Lane. 
  • Funding - 2016-2019 1/4 cent sales tax
  • General Location - Located along North Prince Lane, North of East Chestnut Expressway between North Prince Lane and North Belcrest Avenue 
  • Objectives - Improve stormwater conveyance to mitigate flooding of businesses in the area. City Utilities gas and water service renewals for business along North Prince Lane.