Walnut and Elm Stormwater Improvements

Project Facts

  • Start Date - 8/15/2018
  • Completion Date - 9/29/2018
  • Contractor - Hunter Chase
  • Cost - $74,743
  • Design Engineer - City of Springfield
  • Design Features - 171 linear feet of precast box culvert
  • Funding - Stormwater detention buyout fund
  • Location - Between 1112 and 1122 E Walnut St
  • Objectives - Demolition of approximately 171 linear feet of deteriorated box culvert and installation of new box culvert between Walnut street and Elm Street. The section of box culvert had reached the end of its' useful life and the walls were showing sings of failure. New concrete box was installed to restore the function of the box to full capacity for stormwater conveyance.