Construction Forecast
The schedule below is an estimated timeline of Public Works projects coming forward for bid or construction.
View current contractor bid notifications.
Est. Bid Date | Project | Description | Target Start Date | Est. Duration | Division | Project Manager | Design Consultant | Funding Source |
---|---|---|---|---|---|---|---|---|
Winter 2024 | Scenic Avenue Bridge | Demolition and reconstruction of the Scenic Avenue Bridge. | Early 2025 | 9 Months | Transportation Engineering | A. Nelson | Olsson | 1/8-cent, TBD |
On hold for additional funding | Jefferson Avenue Footbridge | Rehabilitate Jefferson Avenue Footbridge | On hold for additional funding. | 6 months | Transportation Engineering | N. Edelman | Great River Engineering | STBG, 1/4-cent, 1/8-cent, community donations |
Fall 2023 | Grant and Norton Stormwater Project | Stormwater Infrastructure improvements extending from Norton Road to Evergreen Street. | Spring 2024 | 6 months | Stormwater Engineering | J. Codichini | Olsson | LPT, 1/4-cent |
Summer 2023 | Roanoke and Delmar | Stormwater infrastructure improvements | Fall 2023 | 6 Months | Stormwater Engineering | C. Dunnaway | CMT | 1/4-cent, DNR ARPA |
Winter 2023 (Q1) | Battlefield & Luster Signal improvements | Signal replacement and sidewalk reconstruction | Summer 2023 | 60 days | Transportation Management | J. Saliba | 1/8-cent | |
Summer 2023 | Galloway Street Widening | Widen Galloway Street (Luster to Lone Pine) to 3 lanes | Summer 2023 | 12 months | Transportation Engineering | N. Edelman | HDR | 1/4-cent & Governor's Cost Share |
Winter 2022 (Q4) | Busch Building 2nd Floor Engineering Suite Remodel | Remodel of PW Engineering office suite | Winter/Spring 2023 | 2-3 months | Facilities Design & Construction | K. Woodside | Hood Rich Architect | PW/ES departments |
Spring/Summer 2023 | Police Headquarters Roof & HVAC Equipment Replacement and Interior Upgrades | Replacement of roof and HVAC rooftop equipment. Replace carpet and upgrades to conference rooms. | Spring/Summer 2023 | 18 months | Facilities Design & Construction | K. Woodside | In-house | General Fund |
Spring/Summer 2023 | Police Firing Range Demo & New Classroom Building | Demo of existing PEMB and construction of new PEMB classroom facility. | Spring/Summer 2023 | 18 Months | Facilities Design & Construction | L. Morrow | TBD | Law Enforcement Sales Tax |
Fall 2022 | Replacement Fire Station #7 | Demolition of the existing station and construction of a new two-bay, one story Fire Station and other site improvements. | Winter/Spring 2023 | 12 months | Facilities Design & Construction | L. Morrow | Esterly Schneider | LPT, Bond 1 |
Summer 2022 | Bengsch Building Mechanical System Replacement | Assessment of existing HVAC system and complete replacement of facility's mechanical system | Winter/Spring 2023 | 6 months | Facility Design & Construction | L. Morrow | TBD | Health Department |
Summer 2023 | Fire Station #3 Improvements | Various facility improvements including new windows, mechanical and electrical upgrades, bathrooms, turnout gear extractor, fitness area and parking lot repairs | Fall 2023 | 7 months | Facility Design & Construction | L. Morrow | TBD | LPT |
Fall/Winter 2022 | Commercial Street Gateway Signage | Gateway signage/entrances to the Historic C-Street District | Winter/Spring 2023 | 6 months | Facilities Design & Construction | J. Swan | BPR Architects | C-Street TIFF |
Winter 2024 | Historic City Hall Renovation | Renovation of the Historic Structure to provide accessible circulation and facilities, improved HVAC and Electrical systems, and modern office spaces for various City Departments. | Spring 2024 | 18 months | Facility Design & Construction | J. Swan | TBD | LPT, ARPA, City Manager's Contingency |
Spring 2023 | Battlefield & Lone Pine | Intersection, stormwater, sidewalk improvements and signal upgrades | Fall 2023 | Transportation Engineering | N. Edelman | HDR | 1/4-cent | |
Spring 2023 | National Avenue Lane Addition (Walnut Lawn to Battlefield) | Lane addition on southbound lanes including stormwater, sidewalk/trail improvements | 2023 | Transportation Engineering | N. Edelman | CJW | 1/8-cent | |
Fall 2023 | Walnut Lawn & Campbell Intersection | Intersection Improvements including stormwater and sidewalk improvements. | 2024 | TBD | Transportation Engineering | N. Edelman | CJW | 1/8-cent |
2023 | Walnut St. Bridge | Bridge replacement | 2024 | 12 months | Transportation Engineering | A. Haase | CMT | 1/4-cent |
Summer 2024 | Animal Shelter | A new 12,000 sq. ft. animal shelter facility primarily for feline and canine temporary housing and support spaces for animal care and staff. | Fall 2025 | 18 months | Facilities Design & Construction | C. Holland | TBD | LPT, Bond 2 |
2024 | Fire Station #9 Improvements | Various facility improvements such as roof replacement, mechanical and electrical upgrades, and parking lot repairs. | 2024 | 9 months | Facility Design & Construction | K. Diehls | TBD | LPT |